Ball State University in Muncie, Indiana is in the process of installing the largest ground-source heat pump system in the country. It is not supplying just a single building, however. Rather, this is a campus-wide system that will provide heating and cooling for the entire University campus.
The system uses 3,600 vertical bores located in several fileds throughout the campus with more than 1,000 miles of piping for the heat transfer. The first phase of this project is nearing completion, with the system now providing heating and cooling to nearly half the campus.
The University expects to realize $2 million in annual energy costs through the use of the campus-wide geothermal system. Additionally, by removing its old boilers, the University says it will also reduce about 85,000 tons of CO2 emissions annually. Total cost for the project is around $70 million.

written by Kalirren, March 08, 2012
written by Ronald Brak, March 08, 2012
written by Ronald Brak, March 08, 2012
written by Ronald Brak, March 09, 2012
written by Geothermal Minneapolis, March 13, 2012
written by Ron Wagner, March 16, 2012
written by Ronald Brak, March 17, 2012
And as for Indiana not being that cold, I've heard that it is so cold in winter that that water actually changes state and falls from the sky in a strange white precipitate that covers the ground.
written by Carol S., March 20, 2012
written by rex loker, March 20, 2012
Here is the data comparing Epic’s geothermal system with that of Ball State. Hope this is beneficial to you.
1. Both Ball State and Epic are using the same consultant for design of their geothermal systems.
2. The Ball State figures quoted assume phase 2 of their project is complete. Only phase 1 is operational at this time.
3. Phase 1 has 1832 bore shafts 400 feet deep (Epic currently has 2974 bore shafts in use, with an additional 800 coming on line this summer)
4. When phase 2 is complete, Ball State will have an additional 2000 bore shafts 500 ft. deep. (Epic’s planned expansion may include additional bore shafts or ponds/lakes, scope has not yet been determined)
5. The Ball State phase 1 chiller plant has 5000 tons capacity (Epic has approximately 7000 tons of installed capacity)
6. In phase 2, Ball State will be adding an additional 5000 tons of capacity. Construction of phase 2 is to start in 2013. (Epic is planning additional expansion of our system as well)
7. I believe both Ball State and Epic have around 1000 miles of piping in our systems.
8. Ball state’s project cost $70 million for both phases of construction. It is unclear whether that figure includes the cost of decommissioning their coal fired power plant or not.
9. Ball State claims $2 million savings annually
10. Epic does not publish economic data but we firmly believe that geothermal pays for itself within a reasonable time frame since our buildings use significantly less energy than standard office buildings.
written by Charles Young, March 21, 2012
| < Prev | Next > |
|---|
MAR 07
"My name is Charles Young and I am a student from Albion College (In Mi..."
View all Comments